Predecessors -- Integer List field that lists the task ID for predecessor tasks on which the task depends before it can be started or finished. Best Uses -- Add the field to a task view when you want to display or update task predecessors (demonstrate) photo1 - 2 - 3 -- Dependency types -- FS = finish to start FF = finish to finish SS = start to start SF = start to finish Lead Time = time before predecessor target (-) Lag Time = time after predecessor target (+) Example -- "14FS+3d" 14 - predecessor task FS - finish to start dependency +3d - Three day Lag time photo 4 -- Default Values-- Starts with zero dependency - unless it is a subtask (assumes same start date as parent) if only the task number is entered, a finish to start dependency with a zero lag time is assumed photo 5 -- Relating to other Projects -- Predecessor tasks can be tasks in separate projects simply include the path to the project field example: C:\MyDocuments\Bldg_E_Construction.mpp\3FF